Deep Tunnel Sewerage System
Kim Chuan Link Sewers
Contract 2 |
 |
| Owner/Client: |
|
Public Utilities Board |
| Structural Consultant: |
|
CPG Consultants Pte Ltd |
| Description: |
|
The link sewers is constructed to convey wastewater from the existing pumping stations to connect to the TO-2-Bedok Tunnel, via chambers to Drop shaft 'C' structure at Upper Paya Lebar Road/PIE, and then gravitated to Changi Water Reclamation Plants. The contract involved the procurement, supply, construction, testing and commissioning of works associated with the completion of 3km length of sewers ranging from 250mm to 2,000mm diameters. |
| Location: |
|
SINGAPORE |
| Contract Sum: |
|
S$13.7 million |
| Year Completed: |
|
2006 |
| Contract Duration: |
|
24 months (from 3 March 2004) |
|