Punggol-Serangoon Reservoir Scheme Contract 3:
Raw Water Pipeline
(from Seletar Expressway to Upper Pierce Reservoir)
|
| Owner/Client: |
|
Public Utilities Board |
| Structural Consultant: |
|
CPG Consultants Pte Ltd |
| Description: |
|
Construction of water pipeline of diameter 1.6m and approximately 5,600m in length |
| Location: |
|
SINGAPORE |
| Contract Sum: |
|
S$12.65 million |
| Year to be Completed: |
|
2009 |
| Contract Duration: |
|
30 months (from 18 September 2006) |
|