| Singapore Exchange Centre |
 |
| Owner/Client: |
|
Industrial & Commercial Property (S) Pte Ltd
Shing Kwan Realty Pte Ltd
|
| Main Contractor: |
|
Kajima Overseas Asia Pte Ltd |
| Structural Consultant: |
|
Oscar Faber Consultants Pte Ltd |
| Scope of work by BBR: |
|
Prestressing |
| Building Data: |
|
2 Towers – 29 storeys; 1 Podium – 6 storeys; Basement carpark – 2 levels
|
| Location: |
|
Shenton Way, SINGAPORE |
| Contract Sum: |
|
$829,253 |
| Years of Execution: |
|
1998 to 1999 |
| Contract Duration: |
|
12 months |
|