Ayer Rajah Expressway Phases 2A and 2B |
 |
| Owner/Client: |
|
Public Works Department |
| Consultants: |
|
PWD / Meinhardt (S) Pte Ltd |
| Project Description: |
|
Construction & completion of the flyover, road works and bored piling works |
| Contract Sum: |
|
Phase 2A - S$28.9 million }
Phase 2B - S$20.3 million }
|
Joint venture share - 33% |
| Year Completed: |
|
Phase 2A - June 1988
Phase 2B - March 1988 |
| Contract Duration: |
|
Phase 2A - 27 months
Phase 2B - 24 months |