| Interchange at Still Road / East Coast Parkway |
 |
| Owner/Client: |
|
Public Works Department |
| Consultant: |
|
PWD |
| Project Description: |
|
Construction of Interchange at Still Road / ECP |
| Contract Sum: |
|
S$12 million (JV with RDC) |
| Year Completed: |
|
November 1984 |
| Contract Duration: |
|
24 months |
|